Deer Park BESS

The image is indicative location only and is subject to change.
Project Timeline
-
Timeline item 1 - complete
Development - Site Selection
During this phase, potential sites for the Battery Energy Storage System (BESS) are identified and evaluated based on criteria such as proximity to existing electrical infrastructure, environmental impact, land use, and community acceptance. Once the optimal site is chosen, this milestone is marked as complete.
-
Timeline item 2 - complete
Development - Feasibility
In this phase, a detailed assessment is conducted to determine the technical, economic, and environmental viability of the project. This includes analysing energy needs, grid connection possibilities, financial modeling, and risk analysis. Upon confirming that the project is feasible, the milestone is considered complete.
-
Timeline item 3 - active
Development - Planning & Approvals
This phase involves preparing and submitting planning applications to relevant authorities. It includes community consultation, environmental impact assessments, and seeking approval from local councils and other regulatory bodies.
-
Timeline item 4 - incomplete
Development - Post DA Lodgement
After the Development Application (DA) is lodged, this phase focuses on responding to any feedback or conditions set by the authorities. The project team ensures all requirements are met and finalises preparations for the delivery phase. Completion occurs when the DA is successfully processed.
-
Timeline item 5 - incomplete
Delivery - Pre-Construction
In this current phase, the project team prepares for the start of construction. This includes finalising designs, securing contractors, and arranging logistics. The transition to actual construction is carefully planned, and the project is now on track for physical implementation.
-
Timeline item 6 - incomplete
Delivery - Construction
This phase will involve the physical building of the BESS, including site preparation, installation of equipment, and connection to the grid. Safety, quality control, and timelines are crucial. This milestone will be reached once the BESS is fully built.
-
Timeline item 7 - incomplete
Operational
After construction, the BESS will become operational, providing energy storage and discharge as required by the grid or local energy needs. Monitoring and maintenance are ongoing to ensure efficiency and safety. This milestone will be reached once the BESS is fully operational.
-
Timeline item 8 - incomplete
Decomissioning
At the end of the BESS's operational life, this phase involves safely dismantling and removing the equipment, restoring the site, and responsibly disposing of materials. This ensures minimal environmental impact and compliance with regulatory standards.
- The proposed Deer Park Battery Energy Storage System (BESS) will have a capacity of 275 MW / 1100 MWh, providing up to 4 hours of energy storage.
- Designed as a critical piece of energy infrastructure, Deer Park BESS will help secure the energy supply in Victoria.
- It is proposed to be located adjacent to the existing Deer Park Terminal Station.
- We’re still in the early stages – undertaking environmental, cultural, and technical studies before submitting a minor amendment to the existing permit for the approved BESS.
Community Engagement Newsletter
Deer Park Site
490 Christies Road, Ravenhall VIC